Project Overview

  • Part-01 (Buildings & External Works)
    ▪ Buildings Scope: In total, there are 25 Buildings numbered B1 to B24. The
    technical details in the buildings have conventional and specialized
    construction methodologies. As indicative, these works include but are
    not limited to the provision of shallow foundations, RCC works, hollow
    core slabs, steel structure works, shaded structures, high-security steel
    fencing; internal and external finishes for blockwork, plastering,
    waterproofing, painting, doors/windows, tiling, false ceiling and all the
    associated MEP works for plumbing (water supply, drainage, firefighting),
    HVAC, electrical and ELV works. Existing Elevation Renovation: In total, there are 7 Buildings numbered
    E18, E30, E34 to E38 and these are Optional
    ▪ HQ Building- B24(Optional)
    ▪ Provisional Sum
    ▪ Demolition and External Works
    ▪ Infrastructure Scope: The infrastructure scope includes earthwork,
    roadwork, stormwater, drainage, sewerage, water supply, firefighting
    underground services, electrical and ELV works for security network,
    telecom systems, CCTV, street lighting etc.
  • Part-02 Earth Works & Road Works

▪ Earthworks
▪ Truck Road Works (Design & Re measurable)
▪ The total plot area is approximately 664,007 square

Presidential Court (DIWAN)